The construction on Mt. Auburn Street continues with more drainage installation during the week of June 23-27, and work will also take place at the intersection of Arlington and Grove streets. See where the traffic impacts will be in the announcement from the City of Watertown below.
Beginning Monday, June 23, 2025, Newport Construction will resume drainage installation on Mount Auburn Street between Kimball Road and Lloyd Road. Additionally, Newport Construction will be eliminating the existing telephone manhole and installing a new telephone manhole located at the intersection of Grove Street and Arlington Street.
Traffic and Sidewalk Impacts
During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will remain on Mount Auburn Street. Work will take place on the sidewalks, but they will remain open and accessible. Business entrances will be maintained as well. Work in these areas will begin at 7 a.m.
Parking Impacts
Street parking in the construction area on Mount Auburn Street during this phase will be restricted. Construction crews will post parking closure signs in those areas starting at 7 a.m. and will be removing them from the area by 5 p.m. each day.
Equipment for telephone manhole installation may need to park on Wells Avenue overnight.
(Note: All dates are approximate and will be dependent on weather conditions and any testing yet to be performed.)
Resources from the City’s Economic Development Team
During construction in the Coolidge Square area, Watertown’s Economic Development team developed the below graphic to help residents get around Coolidge Square, whether by car, bike, bus, or walking. Keep up-to-date with any road closures, bus stop impacts, or parking limitations in the work detailed above! A larger version of this map can be found at Mount Auburn Street’s project website.
About the Project
The Mount Auburn Street Project will transform the corridor into a Complete Street, providing safe and accessible options for all modes. This project will also provide increased efficiency on the MBTA Bus Route 71, improve traffic operations and pedestrian and bicycle accommodations, improve accessibility in compliance with the Americans with Disabilities Act (ADA), and improved aesthetics.
We will post construction schedules and other work notifications consistently on the project website, and via the City’s social media accounts. You can sign up to receive project email updates here. For questions, please visit the website’s FAQ or email the project team directly.
City of Watertown Department of Public Works