Sidewalk Excavation & Trench Installation This Week on Mt. Auburn Street

More sidewalk excavation this week on Mt. Auburn Street, and trench installation for drainage and trees are also planned. See more information in the announcement from the City of Watertown, below. Sidewalk Excavation Continues At Cambridge Line

Excavation of the eastbound sidewalk and curbing on Mount Auburn Street between Belmont Street and Arlington Street will continue on Monday, October 20, 2025 from 7:00 a.m. to 3:30 p.m. Learn about travel and parking impacts below. Traffic and Sidewalk Impacts

The eastbound sidewalk will be closed for excavation starting on Monday, October 20, 2025 at 7:00 a.m. A bypass sidewalk on the eastbound side will be opened up while this work is being completed.Traffic on Mount Auburn Street will be narrowed and you can expect lane shifts, however traffic will be maintained in both directions. Entrances to driveways and parking lots will be maintained.

Sidewalk and Road Work Will Impact Coolidge Square, East Watertown This Week

The Mt. Auburn Street project continues with sidewalk work from near the Cambridge line to Arlington Street, while drainage work will take place in Coolidge Square. See details in the announcement provided by the City of Watertown. Sidewalk Excavation Begins At Cambridge Line

Excavation of the eastbound sidewalk and curbing on Mount Auburn Street between Belmont Street and Arlington Street will begin on Monday, October 6, 2025 from 7 a.m. to 3:30 p.m. Learn about travel and parking impacts below. Traffic and Sidewalk Impacts

The eastbound sidewalk will be closed for excavation starting on Monday, October 6, 2025 at 7 a.m. A bypass sidewalk on the eastbound side will be opened up while this work is being completed.

Removal of Pavement on Mt. Auburn St. Begins This Week

The process of removing the old asphalt to prepare for the repaving of on Mt. Auburn Street will begin this week. Also, hydrant installation and sidewalk pouring will take place in the East End. See details in the City of Watertown’s announcement, below. Sidewalk Concrete Installation and Excavation

Sidewalk concrete installation and pouring will take place on the westbound side of Mount Auburn Street, between Belmont Street and Prentiss Street from 7:00 a.m. to 3:30 p.m. Concrete pouring is scheduled to take place between Belmont Street and Prentiss Street on Monday, September 15, 2025.

This Week’s Mt. Auburn St. Construction Begins After Labor Day

Construction on Mt. Auburn Street will take a day off for Labor Day, and resume with sidewalk and drainage work on Tuesday. See more information in the announcement from the City of Watertown. Sidewalk Concrete Installation

Sidewalk concrete installation and pouring will take place on the westbound side of Mount Auburn Street, between Belmont Street and Keenan Street from 7:00 a.m. to 3:30 p.m. Concrete pouring is anticipated to begin between Belmont Street and Francis Street on Wednesday 9/3/2025. Notices have been provided to the properties directly affected within the pouring area.

UPDATED: Removal of Shade Trees on Mt. Auburn, Keith Street Approved by City Manager

(CORRECTION: The story has been updated to include two areas where trees will be removed. The previous story only referenced Keith Street). A total of 17 shade trees off in East Watertown will be removed as part of the construction projects after City Manager George Proakis gave his approval. The trees to be removed include nine along Mt. Auburn Street as part of the reconstruction of the street and eight on Keith Street located on a property where a home is planned to be built.

The trees on Mt.

Sidewalk Excavation, Drainage Work Continues on Mt. Auburn St.

During the week of July 21, sidewalk work will continue in East Watertown, and Drainage Work will take place in Coolidge Square. See more details in the announcement from the City of Watertown. Sidewalk Excavation Continues

Excavation of the westbound sidewalk on Mount Auburn Street between St. Mary Street and Prentiss Street will begin Monday, July 21, 2025 from 7:00 a.m. to 3:30 p.m. Learn about travel and parking impacts below. Traffic and Sidewalk Impacts

The westbound sidewalk will be closed for excavation starting Monday, July 21, 2025 at 7:00 a.m. A bypass sidewalk on the westbound side will be opened up while this work is being completed.

Mt. Auburn St. Project Will Impact Arlington/Grove Intersection This Week

The construction on Mt. Auburn Street continues with more drainage installation during the week of June 23-27, and work will also take place at the intersection of Arlington and Grove streets. See where the traffic impacts will be in the announcement from the City of Watertown below. Beginning Monday, June 23, 2025, Newport Construction will resume drainage installation on Mount Auburn Street between Kimball Road and Lloyd Road. Additionally, Newport Construction will be eliminating the existing telephone manhole and installing a new telephone manhole located at the intersection of Grove Street and Arlington Street. Traffic and Sidewalk Impacts

During this work, you can expect temporary lane shifts and possibly lane closures, but one travel lane in each direction will remain on Mount Auburn Street.