Installation of Geothermal Wells to Begin Soon at Watertown High School, Will Take 4-5 Months

The following information was provided by Vertex, the project management firm for the Watertown High School project:

Starting the week of August 5th, you can expect to see the mobilization of geothermal well drilling rigs at the new Watertown High School Building Project. This is an exciting milestone for the project, as the before mentioned geothermal wells will aid in the project’s goal of being a net-zero energy building. The geothermal wells, once installed, will provide heating and cooling to spaces in the new high school including the gymnasium, the auditorium, and other community spaces throughout the school. The project expects these drilling rigs to be on site for approximately 4-5 months to complete 14 wells to approximately 900 feet deep. What to expect in the coming months, starting the week of August 5th:

–  Geothermal Well Drilling Rigs on site from 7AM-5PM

–  Equipment will be located on the corner of Columbia and Common Streets within the construction fence.

Milestone Celebrated in Creation of a New, Net Zero Watertown High School

The final beam is bolted into place at the new Watertown High School. (Photo by Charlie Breitrose)

A steel beam, with a small tree on top and an American flag flying from it, was lifted hundreds of feet into the air by a crane and bolted into place marking the topping off of the new Watertown High School project. The ceremony marked the finish of the construction of the frame for the new school, said Superintendent Dede Galdston, which is going up on the site of the old high school. “As I stand here before this impressive structure, it is essential to reflect on the journey that brought us to this moment,” Galdston said. “The vision for this new school building was born out of a shared commitment to fostering an environment where our children can thrive academically, socially, and emotionally.”

Road Near High School Construction Site Closing for 2 Days

The following announcement was provided by Watertown’s project management firm, Vertex:

As we continue to progress the new high school project, Brait Builders and their subcontractors are planning to continue new utility work in Broadway this Thursday 6/6 and Friday 6/7.  This will require that we close the road to through traffic from 7 a.m. to 3 p.m. from the intersection of Broadway and Columbia Street to Russell Avenue. 

Residents of that area of the street will have access to and from their driveways. The contractor will have someone there to ensure safe access as needed. As a quick update, today the project reaches another milestone as we install the topping off beam on the Common Street side of the building. Things continue to progress well overall and we move towards being enclosed and weathertight this Fall.

Sign a Part of the New Watertown High School, Ceremony Will Celebrate Construction Milestone

An overhead view of what the new Watertown High School will look like. (Courtesy of Watertown Public Schools)

A major milestone will be reached this week in the Watertown High School project when the last beam for the steel structure will be put into place. A topping off ceremony will be held on Wednesday, and the public is invited to come before hand and sign the beam, and to attend the ceremony. The Watertown Public Schools sent out the following information:

Major WHS construction news! A topping off ceremony will be held at 4 pm on Wednesday (6/5/24). 

The public is also invited to sign the ceremonial beam. 

Monday/Tuesday : 2-5 pm (Broadway construction gate)

Wednesday: 3-3:45 pm (Common Street gate). 

Sharpies will be provided

Sidewalks Closing on Common Street for High School Project

The project managers for the Watertown High School project, Vertex, announced that a portion of the sidewalk near the high school construction site will be closed temporarily. Vertex provided the following announcement:

Please note that the permanent fix of the sidewalk at the intersection of Spring & Common Street is expected to take place this Friday 4/19/24 (weather depending). That portion of the sidewalk will be temporarily unavailable on Friday 4/19/24 and will be returned to service on Saturday 4/20/24. The above image shows the exact location where the sidewalk will be repaired on the High School side of Common Street.

A Couple of Late Evenings of Construction at Watertown High School

The following announcement was provided by project management firm Vertex:

Progress continues at the site of the new Watertown High School Project with work ongoing both inside the new building structure and around the site. In the coming days please be aware that the site may require work to extend beyond 7 p.m. due to ongoing concrete slab placements. The construction team has several slab placements on the schedule for this week and potentially long shifts on the following dates:

Wednesday April 10th

Friday April 12th

These slab placements are beginning at 7 a.m. on each of the above dates. The duration required for the slabs to be finished is dependent on the outside air temperature and weather conditions on the day of placement. Therefore, it is likely that the effort to finish the slabs once placed will continue into the evening on each of the above listed dates and have the potential to extend past 7 p.m. into the evening.

Work Moving Ahead on New High School, Likely to Extend Into the Evening Some Days

The steel frame of the gymnasium at the new Watertown School before the slab is placed on the area in early April. (Courtesy of Vertex)

The following announcement was provided by Watertown’s project management firm, Vertex:

The new WHS Project Site remains busy as the site preparation and steel detailing continues. Above is a current view of the steel erection progress (view of the new gymnasium space) ahead of our upcoming slab on deck placement in this area next week. We have several slab placements on the schedule for next week proposed for the following dates:

Monday April 1st : Gymnasium

Wednesday April 3rd

Thursday April 4th

These slab placements are beginning at 7 a.m. on each of the above dates. The duration required for the slabs to be finished is dependent on the outside air temperate and weather conditions on the day of placement.

High School Demolition Going Slower Than Anticipated, Work Continues This Week

The remaining part of the old Watertown High School Building. (Courtesy of Vertex)

The following information was provided by project management firm Vertex:

The Watertown High School project team continues to be hard at work progressing the demolition of the existing high school and installing new foundations in preparation for our first steel deliveries in January. 

As you can see from the picture above taken from across Common Street at the corner of Spring Street, there continues to be structure remaining at that corner. Between recent challenging weather conditions, and a decision to use more “handwork” for demolition of areas closest to the cemetery and the street, we are progressing a little slower than we had hoped.  With that said, we have agreed that the Contractor can continue with onsite demolition Saturday 12/30/23 within normal working hours allowed by the City, which is 8 a.m.-4 p.m. 

There will not be any loading out of materials so the Community will still have the holiday reprieve from trucking. All normal trucking and construction activities will resume on Tuesday 1/2/24 at 7 a.m.

We appreciate your continued patience and support as we work together to bring the new Watertown High School to fruition.  There will be a lot of exciting updates to share with you in 2024!