Asbestos Abatement Will be Costly in School Projects, Soil for Foundations in Good Shape

Asbestos was found deep in the walls of Hosmer Elementary School, which will result in higher costs of demolition when the new school is built.

Architects gave the School Building Committee some good news and some bad news with the costs related to hazardous material removal and the grounds where foundations will be built for the upcoming construction projects. In preparation for the construction projects at Watertown’s three elementary schools, architects have been looking at the conditions for demolition of the current schools, and to put in foundations for the new ones. The Bad News

When the schools were examined the schools for hazardous materials some asbestos was found in some hidden places, said Scott Dunlap, project architect for Ai3 Architects. The school with the most was Hosmer Elementary. “What we found at Hosmer we have only seen it a couple times,” Dunlap said, who described a layer of asbestos buffering between the exterior brick wall and the cement blocks inside.

Architects Discuss School Gardens, Playgrounds & Outside Learning Spaces

A drawing showing the outdoor learning space outside Lowell Elementary School. The amenities surrounding Watertown’s three elementary schools after they are rebuilt or renovated are taking shape, but the School Building Committee and others have some concerns about handicap accessibility, deliveries and more. The designers of the town’s three elementary schools, Ai3 Architects, showed the School Building Committee details of the plans for the playgrounds, outdoor learning spaces, school gardens and even delivery areas at the Aug. 21 meeting. Gardens & Outdoor Learning Areas

The designers are working with teachers, staff and the district’s School Garden Coordinator, Judy Fallows, to help design the school gardens.