See How the Commonwealth Ave. Bridge Work Impacts the 57 Bus, BU Bridge

The Massachusetts Department of Transportation (MassDOT) is continuing to remind members of the public that weather permitting, trolley service on the MBTA’s Green Line B Branch near the Commonwealth Avenue Bridge and access for private vehicles to the Commonwealth Avenue and Boston University Bridges is anticipated to resume by the middle of the upcoming week as a major phase of construction on the Commonwealth Avenue Bridge is expected to be completed. MassDOT sent out the following information:

Throughout Friday and Saturday, some of the final construction-related activities including placing rail and grout were taking longer than planned, and weather conditions including rain delayed some of the pouring of concrete.  On Sunday, crews have been continuing to work 24/7 to place new rail and concrete on areas of the deck. The concrete will need to cure for at least 24 hours and the rail must be tested prior to service. Sunday night, crews placed waterproof membrane on the bridge surface, re-stringing the catenary wire that powers the MBTA’s Green Line, and conducting additional track related work. Tomorrow, crews will be putting in place the first-level of pavement on the eastbound side of the Commonwealth Avenue Bridge. The full upcoming schedule of travel impacts as follows:

Through the middle of the upcoming week: the BU Bridge and Commonwealth Avenue Bridge are anticipated to remain closed to private vehicles.

Mass Pike Opening All Lanes Monday, Work on Commonwealth Ave. Bridge Continues

The Massachusetts Department of Transportation (MassDOT) announced that crews will return I-90 (the Massachusetts Turnpike) in Boston to its normal configuration of four lanes of traffic in each direction by 5 a.m., Monday, August 7, almost three weeks faster than originally scheduled as part of the Commonwealth Avenue Bridge Project. 
MassDOT sent out the following release:
The schedule for completing the remaining construction work and the other travel impacts remain unchanged; crews are on schedule, and as detailed below, impacts to travel along Commonwealth Avenue and local roadways, as wells as service impacts to the MBTA’s Green Line B-Branch and bus routes are expected to continue through Monday, August 14. “The hard work of our crews and contractors is allowing us to meet this important milestone ahead of schedule and open all four lanes in each direction on I-90 in Boston in time for the Monday morning commute,” said Transportation Secretary and CEO Stephanie Pollack. “Our team has designed this major construction project in a way that considers the needs of the traveling public, as well as residents of the Greater Boston area, and we are pleased with the progress of work so far. We appreciate the continued support and patience of the traveling public and will continue to conduct our operations in ways that seek to minimize our impact on the local community and all those who travel throughout the Commonwealth Avenue/ Boston University region in Boston.”
“MassDOT’s engineering and construction staff have been working closely with the contractor throughout this project and we collaboratively modified the sequencing of key work to create opportunities for removing the 440-ton crane on the Pike more efficiently than originally planned,” said Acting Highway Administrator Jonathan Gulliver. “This change will lead to the return of I-90 to full capacity, which is four lanes in each direction, almost three weeks earlier than previously scheduled. This is an important but interim milestone and while we are pleased with the progress of construction so far we still have much work to do to complete our operations this summer.”

Watertown Shuttle Could Start Running in Fall, or May Wait Until Spring

Watertown’s first shuttle will likely run down Pleasant Street to Watertown Square and could start as soon as this fall, but may have to wait until the nice weather arrives in 2018. On Wednesday night, members of the Town Council’s Ad Hoc Committee on Transportation were eager to find out when they could see Watertown’s first shuttle. The Watertown Transportation Management Association (TMA) will run the shuttle, and if all goes right the first shuttles could start rolling this fall, said Allison Simmons, a consultant from Ease Consult hired by the Town to form the TMA. However, it may have to wait until spring. To get the shuttle started this fall, Simmons said, the Watertown TMA board would have to approve the shuttle pilot at its August meeting and get members to agree to fund it soon after.

Mass Pike Will Close Briefly Thursday Afternoon in Allston

The Massachusetts Department of Transportation (MassDOT) announced that Thursday, Aug. 3, between the hours of 1 p.m., and 2 p.m., crews will adjust the traffic configuration on I-90 in the area under the Commonwealth Avenue Bridge so that later on all vehicles, east and westbound, will be traveling on what drivers know as the normal eastbound side of the highway. During this operation, it will be necessary to temporarily stop all traffic for a short, approximately 20 minute period on I-90 westbound in the area of the Commonwealth Avenue Bridge in the Allston area of Boston. During this period, I-90 eastbound will continue to have two lanes of travel open. At this hour, and until this afternoon, there will continue to be two lanes of travel open on the east and westbound side of the highway in the Allston area.

Commonwealth Avenue Bridge Project Will Impact Drivers, T Users, Amtrak and More

The replacement of the Commonwealth Avenue Bridge will cause delays and detours for drivers, MBTA users, and others during construction. The construction will impact the Mass Pike, Commonwealth Avenue, the BU Bridge, Hubway, the MBTA Green Line and buses, the Commuter Rail and Amtrak. The Massachusetts Department of Transportation (MassDOT) sent out the following information:

This is a reminder that the 2017 Construction Shutdown for the Commonwealth Avenue Bridge Replacement Project (http://www.massdot.state.ma.us/highway/HighlightedProjects/CommonwealthAvenueBridgeReplacement.aspx) is beginning at 9:00 PM on Wednesday, July 26, and will continue through 5:00 AM on Monday, August 14. Please note the construction-related impacts below:

For Drivers:

•      I-90 (Mass Pike) Users:
From 9:00 PM on July 28 to 5:00 AM on August 7:

•      I-90 between the Allston Interchange and the Beacon Street Overpass in Boston will be reduced to two lanes in both directions during peak hours (additional lane closures during off-peak hours, see below). •      The I-90 Eastbound on-ramp from Cambridge Street/Soldiers Field Road will be closed.

MassDOT Holding 2 Meetings About Commonwealth Ave. Bridge Replacement

The Massachusetts Department of Transportation announced it will be hosting two Pre-Construction Public Meetings for the Commonwealth Avenue Bridge Replacement Project:

Tuesday, July 11, 6:30 PM Boston University College of General Studies Jacob Sleeper Auditorium (Lower Level, Room 129) 871 Commonwealth Avenue, Boston, MA

Thursday, July 13, 6:30 PM Newton Free Library, Druker Auditorium 330 Homer Street, Newton, MA

The same presentation will be delivered at each meeting, so participants may choose the most convenient date or location. Please join the Massachusetts Department of Transportation (MassDOT) for a presentation on the upcoming major construction activities for the Commonwealth Avenue Bridge Replacement Project. MassDOT and project team staff will describe the Summer 2017 Construction Shutdown (July 26 – August 14) in more detail, review detour routes, and respond to questions. During the shutdown, there will be significant service impacts to all modes of transportation along Commonwealth Avenue in the BU/Saint Paul Street neighborhood and on I-90 (Mass Pike). Please visit the project website, www.mass.gov/MassDOT/CommAveBridge, for a full schedule of the upcoming closures, detour routes and maps, and to sign up for project updates.